Craig Pullen Consulting
Contract Value
£5,011,966
Suitable for SMEs
Yes
Suitable for VCSEs
Yes
Program - Works to be carried out between 9 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 09 Sept 2022 - 13 October 2022 [5 weeks]
Adjudication & contractor interviews - 14 October - 3 November 2022 [2 weeks]
Second Stage Tender - 4 November 2022 - 15 December 2022. [6 weeks]
Adjudication & contractor appointment - 15 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest
Construction work for college buildings (CPV 45214300)
United Kingdom (UK)
Craig Pullen Consulting
Further information on this tender from Craig Pullen Consulting when you create a FREE Account
View all of your tenders, see forthcoming opportunities, access data/reports.